A phase-by-phase look at the timeline from first conversation to move-in — and what keeps a build on schedule.
Nationally, the average new house takes well under a year to build — but that average is dominated by production homes built from repeatable plans. A one-of-a-kind home involves more design, more decisions and more custom fabrication, and the schedule reflects that.
| Phase | Typical length | What happens |
|---|---|---|
| Lot & feasibility | 2–8 weeks | Evaluating the lot’s zoning, slope, trees and utilities; early budget range |
| Design & engineering | 2–5 months | Floor plan, elevations, construction drawings, structural engineering |
| Budgeting & selections | Overlaps design | Detailed pricing; choosing finishes, fixtures and long-lead items |
| Permitting | 1–3 months | Building, demolition, tree and site permits; varies by city |
| Construction | 12–18 months | Site work and foundation through framing, rough-ins, finishes and inspections |
| Final walkthrough | 2–4 weeks | Punch list, certificate of occupancy, move-in — then the one-year warranty begins |
Typical ranges for luxury custom homes in Buckhead, Sandy Springs, Brookhaven and nearby. Every project is scheduled individually.
Our process is built around making the big decisions early. We evaluate the lot before design begins, finalize the plan and budget before construction, and help clients make selections ahead of when they’re needed on site. And because you work directly with partners Rob Anagnostis and Paul Marotte — not a rotating cast of project managers — questions get answered quickly.
See how it works on our custom home building page, or browse finished homes in our case studies.
Construction alone sometimes can for a smaller, simpler home. For a luxury custom home, it’s more realistic to plan on 12 months or more of construction plus the design and permitting time before it.
Usually, yes — depending on scope. See our renovations and additions page.
Work backward roughly two years and reach out early. If you already have a lot, the clock starts sooner.
Tell us where you are in the process. We’ll map out a realistic timeline from today to the day you get the keys.